Project Planning States
Status:Â Live
Project Planning States
Â
Introduction
This describes the transition a project takes from the sales process to the product team. In order to properly plan the team resources, this gameplan should be followed.
Â
Project States
We follow the RSC process. There are three different planning states a project can be in:
On the Radar
Scheduled
Comitted
Â
1. On the Radar
Sales wants the Product Team to be aware that there might be a project coming up in the future.
Required Information
What is the project about
How likely is the project at the moment Likely moderate Unlikely
Time Frame rough
Start Date
Estimation
Target Date
Process
Sales fills out the Hubspot deal with all minimum the required information
Sales creates a https://9y-media.atlassian.net/wiki/spaces/9RPBK/pages/2421424129
The Resource Manager will put the project on the roadmap in Runn, so that it is on the PT radar
The Resource Manager pings back sales that it’s on the radar, by marking the Slack thread with a 🗓 icon
Outcome
No further action is taken by the PT
If there are questions by the sales person, like, can we do this project in June, it goes into Schedule ticket status
Â
2. Scheduled
Sales wants the Product Team to schedule the project according to the client wishes and the available resources.
Required Information
What is the project about
How likely is the project at the moment Likely moderate Unlikely
Time Frame desired (The time frame the customer would like to have)
Start Date
Estimation
Target Date
Resources
Which Technology is it based on?
What is the rule of thumb estimation?
Do we need design?
How important is the project high normal low
Process
Sales creates a https://9y-media.atlassian.net/wiki/spaces/9RPBK/pages/2421424129
||:
The Resource Manager will bring the project to the weekly Team Planning JFThe desired time frame will be discussed
The JF gets back to Sales with a possible time frame
Sales double checks with the client and either brings up a new suggestion or agrees to the suggested time frame
:|| [repeat 2-4 until agreed]The slack thread is marked with 🗓 once everything is agreed upon and the resources have been planned
Outcome
A scheduled and planned project that only requires green light if it does not change
Sales has a commitment that they can give the client
Â
3. Committed
Sales gives the green light to the project based on the Schedule Status.
Required Information
What is the project about
How likely is the project at the moment Likely moderate Unlikely
Time Frame agreed (The time frame of the previous state)
Start Date
Estimation
Target Date
Resources
Which Technology is it based on?
What is the rule of thumb estimation?
Do we need design?
How important is the project high normal low
Green Light
Process
Sales creates a https://9y-media.atlassian.net/wiki/spaces/9RPBK/pages/2421424129
The Resource Manager double checks the information
The Resource Manager informs the Team Planning JF
Outcome
The project is ready to go at the agreed start date
PM will schedule a hand over
Â
Planning States and Time Line
Ongoing Projects & Projects coming up next week
Committed State (must have)
If not all the conditions are met, the project is pushed a week unless it is explicitly decided to take the risk and keep it (by the PT)
Projects coming up within the next month
Scheduled State (should have)
On the Radar State (must have)
Projects coming up within 3 months
On the Radar State (should have)
Â
Owner
Reviewer
Â